Agenda Title:

Approve Change Order #1 to Scull Construction Service Inc for Canyon Lake Dam Reconstruction, Project No. 08-1743 / CIP No. 50739, for an increase of $33,299.04.

Summary:

Increase to contract due to postponement of project. 

Funding Source & Fiscal Impact (if applicable):

0122 Vision Funds